WOODLAND HILLS SANITRY DISTRICT     

INCOME STATEMENT

September 30, 2014       

 

    

GENERAL INCOME AND EXPENSE

 

WATER INCOME

 

Water Sales                       5261.00   

Late Charges                           100.00

 

TOTAL                                  5,361.00

 

Actual Payments                                                 6,285.82

 

TOTAL WATER INCOME                                                                                   6,285.82

ASSESSMENT                                                                                                                                             1,852.32

TOTAL CUSTOMER PAYMENTS                                                                                                    $8,138.14

 

GENERAL EXPENSES

 

Black Hills Power & Light                      521.52 (Utility)

Lois Lund                                              475.00 (Contract)                                               

Clearwater Consulting                                       650.00 (Contract)                                                

Midcontinent Testing                                                    414.00 (Lab fees)                     

 

TOTAL GENERAL                                                                                                                                                                                   2,060.52

         NET                                                                                                                                               $4,225.30       

PROJECT INCOME AND EXPENSE

 

LOAN INCOME

 

DENR Draw 13                                                                  1,319.00 (to date we have received $141,463.92)                  

 

PROJECT EXPENSES

 

AE2S invoice 13                                                                                            1,169.00

Clearwater Consulting                                                                                     150.00

                                                                                      

 

TOTAL PROJECT EXPENSES PAID FOR SEPTEMBER                    $1,319.00

 

 

 

 

 

 

 

 

 

 

 

PENDING PROJECT EXPENSES (submitted to BH Council) 

 

AE2S invoice 14                                         $3,865.90

Clearwater August                                    210.00

 

                                              $4,075.90

 

Full accounting of draws and expenses are reflected on the spreadsheet that Ali prepares.  This will be emailed to all board members upon receipt.               

 

 

 

 

ROADS INCOME AND EXPNESE

 

INCOME

 

Tax deposit $67.95 – Was deposited in water account, telephone transferred on 10/8/14

 

EXPENSE

 

No expenses

 

 

 

Balance in checking - Great Western Bank - WHSD           119,225.00 (includes 22,155.20 upgrade assessment )        

Balance in checking – Great Western Bank – Roads                                    58,795.60          

Balance in savings – Great Western Bank – Roads                                              2,904.55

                                                                                                    $180,925.15

 

 

Gallons pumped August 2014           671,900                    Gallons reported                          489,134

Gallons pumped September 2014      562,500                    Gallons reported                          372,418

                                                                                      (thru 10/8/14        

                                                                                               1unpaid)

 

 

 

SEPTEMBER PAST DUE                                                        OCTOBER UNPAID

 

NONE                                                       Adam, Mike    

     

                                                                      Postcard sent